The Proposed Nine Steps Explained
Proposed Step 1
The proposal for Step 1 centers on identifying key stakeholders and functions within the asset owner’s organization. This step would involve clearly defining the scope of information to be managed and capturing its intended purposes. In addition, asset owners should incorporate the viewpoints of external stakeholders – including regulators, investors, and insurers – to ensure that all relevant requirements and expectations are considered.
Proposed Step 2
The proposal for Step 2 focuses on determining all necessary components for producing, maintaining, and utilizing asset information models – such as information requirements, standards, methods and procedures, and a common data environment.
Proposed Step 3
For Step 3, the proposal is to focus on project initiation activities. These closely align with the assessment and need step in part 2 of ISO 19650. However, rather than starting from scratch for each project, this step would involve assembling the foundational components established in Step 2 and tailoring them to the specific needs of the project.
Proposed Steps 4–7
Steps 4 through 7, as proposed, largely mirror Steps 2–5 of the existing processes. If you are currently involved in preparing invitations to tender, responding to tenders, managing appointments, or mobilizing teams, the unified process should not significantly change your current way of working. However, some terminology updates are suggested, such as replacing procurement-specific terms like “tender” with more inclusive language, reflecting both internal and external appointments.
Proposed Step 8
Step 8 aims to consolidate Steps 6 and 7 from the delivery phase and Steps 6–8 from the operational phase into a single information production step. While this might appear to increase activity, most tasks are already duplicated in the current process, and only one new activity is being introduced, which applies only under specific circumstances. Overall, proposed changes for information production are minimal, including only minor terminology updates, since the output remains the information produced.
For most appointed parties whose primary responsibility is information production, the unified process is expected to have little impact on current practices.
Proposed Step 9
Finally, Step 9 corresponds to the project close-out step in part 2 of ISO 19650. No substantive changes are suggested for this step, apart from its repositioning from Step 8 to Step 9 in the unified process.